Measurement Book (MB) & Running Account (RA) Bills in Civil & Infrastructure Tenders
Understand how e-MB Measurement Books verify completed physical civil quantities before Running Account (RA) interim contractor payments are released.
In This Guide (Quick Navigation)
In civil works, municipal roads, and electrical projects spanning months, contractors receive periodic interim payouts through Running Account (RA) Bills backed strictly by verified entries inside an official Measurement Book (MB / e-MB).
Meaning & Definition
A Measurement Book (MB) is an auditable engineering ledger (now digitized as e-MB in CPWD/PWDs) where the Junior Engineer/Assistant Engineer physically measures length, breadth, depth, concrete grade, or cable metres executed at site before releasing progress payments.
Why It Matters for Bidders & Suppliers
Without joint measurement sign-off inside the MB + mandatory material quality cube/bitumen test certificates, treasury software halts RA bill payment cleanly.
Detailed Explanation & Procurement Rules
Deductions Shown on Every RA Bill Voucher
Expect statutory deductions on every RA bill: Income Tax TDS (1% individual/HUF, 2% companies under Sec 194C), GST-TDS (2% under Sec 51), BOCW Labour Cess (1%), Security Retention (as per contract), and any Secured Advance adjustment.
Common Mistakes to Avoid
- ⚠Failing to accompany site engineers during initial buried foundation/trench measurements before backfilling earthwork—unmeasured concealed work faces audit disallowance!
Frequently Asked Questions
What is Secured Advance in RA billing?
On qualifying large CPWD works, buyers advance up to ~75% of assessed non-perishable material cost (steel/cement) stacked cleanly at site against indemnity bonds before installation.