Decoding Tender Payment Terms: Milestone Split (`80/20`), Retention, Statutory TDS & Release Rules

A bid offering "70% on Supply + 20% on Installation + 10% after 12 months Warranty" ties up cash far differently than GeM 100% post-CRAC terms. Model working capital before bidding.

Payment Terms, Deductions, Holdback & Milestone Billing Wording
By Raghavendra Kulkarni Reviewed by SCL Procurement Legal & Compliance Desk
Portal Coverage
GeM, CPPP & State Portals
Section
BOQ & Docs
Access
Free Open Guide
Standards Status
Verified 2026 Rules
In This Guide (Quick Navigation)

Profit margin in public contracts is inseparable from cash conversion cycle—determining how many weeks of bank OD interest you bear between paying OEM suppliers and receiving treasury NEFT credits.

Meaning & Definition

Payment Clauses govern billing triggers (Delivery / Installation / Monthly Attendance / Quarterly SLA), percentage split across stages, statutory tax withholding, and retention money release after Defect Liability Period.

Why It Matters for Bidders & Suppliers

Underestimating a 6-month commissioning holdback or forgetting mandatory deductions (2% Section 51 GST-TDS, 1%–2% 194C TDS, 1% BOCW Cess on works) creates acute cash crunches on multi-crore orders.

Detailed Explanation & Procurement Rules

Standard Payment Structures in Indian Tenders

GeM Standard Goods: 100% payment within 10 calendar days of CRAC generation (GTC Rule). Complex Turnkey/IT Bids: often 60%–80% on Delivery + Site Verification (PRC), 20%–30% on Installation/Go-Live (CRAC), and final 10% after 90 days stabilization or against Bank Guarantee (PBG).

Works Contracts (PWD/CPWD/PHED): Monthly Running Account (RA) Bills subject to 5%–10% Retention / Security Deposit holdback (released half on completion and balance after 12-month DLP unless replaced by BG).

Step-by-Step Process

  1. 1 Highlight exact billing documents demanded per milestone (Tax Invoice, e-Way Bill, PRC/CRAC, Installation Report, EPF/ESIC ECR Challans for service bills).
  2. 2 Verify whether TReDS invoice discounting is active for your GeM / PSU buyer to turn accepted invoices into 48-hour cash.
  3. 3 Maintain neat GST-TDS Credit acceptance inside your GST Portal Electronic Cash Ledger (TDS & TCS Credit Received) every quarter.

Common Mistakes to Avoid

  • ⚠Issuing invoices omitting Buyer Department GSTIN, GeM Contract No., or Consignee HSN classification—guaranteeing treasury audit rejection!

Frequently Asked Questions

Can a PSU retain 10% cash security ON TOP OF a 5% PBG without limit?

Under standard GFR/DoE contracts, total performance + retention security is normally capped (3%–10% per NIT/DoE limits); check SCC wording closely because works contracts often recover retention up to 5% inclusive of initial EMD/SD.

Official References & Government Sources

Editorial Verification & Publishing Metadata
Published: 20 Oct 2026 · Last Reviewed: 10 Nov 2026